A newly bought slew crane needed a major inspection on site before its first job — handled from initial scope to final sign-off, engineer-supervised and fully documented.
A newly purchased Demag AC100 needed a major inspection completed on site in the Whitsundays before it could take its first job.
Everything from initial scope to final sign-off, including independent engineering and NDT.
A full major-inspection scope defined with independent structural engineers.
Engaged independent structural engineers for a complete inspection and NDT integrity tests; dismantled the crane on site and catalogued every component; rushed critical parts off site to keep lead times tight; reassembled under engineer supervision with load checks — every step documented and engineer-signed.
Sunshine Coast · Brisbane · Gold Coast · Bundaberg · Gladstone · Mackay
Plus remote, interstate and international mobilisation.
We'll scope it, quote it fixed, and give you a date we'll stand behind.